Supplemental Tests
Test 7 - This tests the inter-winding insulation between primary (H) and
secondary (X). Short H1 to H2 and short X and Y windings to themselves.
Connect HV cable to H, Red lead to X and Blue lead to Y. Test mode is UST-R.
Test 8 - This tests the inter-winding insulation between primary (H) and
secondary (Y). Short H1 to H2 and short X and Y windings to themselves.
Connect HV cable to H, Red lead to X and Blue lead to Y. Test mode is UST-B.
Test 9 - This is a cross check test. Remove shorting lead from H1/H2.
Connect HV lead to H1. Short X and Y windings together and connect to H2.
Connect Red lead to H2. Test mode is Test mode is GSTg-R.
Test 10 - This is a cross check test. Remove shorting lead from H1/H2.
Connect HV lead to H2. Short X and Y windings together and connect to H1.
Connect Red lead to H1. Test mode is Test mode is GSTg-R.
Bushing Tests
Test 11 - This is the test of the C1 insulation on the H1 bushing (only performed
if the bushing has a capacitance tap). All shorting leads must be removed. HV
lead is connected to H1 and Red lead is connected to the test tap. Test mode is
UST-R.
Test 12 - This is the test of the C1 insulation on the H2 bushing (only performed
if the bushing has a capacitance tap). All shorting leads must be removed. HV
lead is connected to H2 and Red lead is connected to the test tap. Test mode is
UST-R.
G
CAUTION
Bushing test taps have very limited insulation and should
generally be energized at reduced voltage levels. If the PT or
bushing manufacturer does not specify a test voltage level
use no more than 500 volts (0.5kV).
Test 13 - This is the test of the C2 insulation on the H1 bushing (only performed
if the bushing has a capacitance tap). All shorting leads must be removed. HV
lead is connected to the test tap and Red lead is connected to the H1 bushing.
Test mode is GSTg-R.
Test 14 - This is the test of the C2 insulation on the H2 bushing (only performed
if the bushing has a capacitance tap). All shorting leads must be removed. HV
lead is connected to the test tap and Red lead is connected to the H2 bushing.
Test mode is GSTg-R.