Description of Tests
Transformer Overall Tests
Prior to the overall insulation tests, short all high side (H) bushings together and
short all low side (L) bushings together, keeping both windings separated.
Remove ground connections from neutral bushings.
Test 1 - This is a measurement of the insulation between the transformer high
voltage winding and the transformer tank, plus the insulation between the high
voltage winding and the low voltage winding, both measured in parallel.
Connect the HV cable to the H winding and connect the Red lead to the X
winding. Test mode is GST-GND.
Test 2 - This is a measurement of the insulation between the transformer high
voltage winding and the transformer tank. Connections are exactly the same as
for Test 1. Test mode is GSTg-RB.
Test 3 - This is a measurement of the insulation between the transformer high
voltage winding and the low voltage winding. Connections are exactly the same
as for Test 1 and 2. Test mode is UST-R.
NOTE: Once Tests 1, 2 and 3 are completed, Line 4 will populate with values
calculated by subtracting Test 2 from Test 1. This is applicable for
values of capacitance, current and watts. Line 4 is a calculated
comparison to the direct measurements of Test 3. Values on these two
lines should be essentially the same. If they are not, re-check all
connections and verify the proper operation of the test set. If Test 3 and
Line 4 vary by more than 2%, the Insulation Rating (IR) will
automatically populate with B (Bad).
Test 5 - This is a measurement of the insulation between the transformer low
voltage winding and the transformer tank, plus the insulation between the low
voltage winding and the high voltage winding, both measured in parallel.
Connect the HV cable to the low side (L) winding and connect the Red lead to
the H winding. Test mode is GST-GND.
Test 6 - This is a measurement of the insulation between the transformer low
voltage winding and the transformer tank. Connections are exactly the same as
for Test 5. Test mode is GSTg-RB.
Test 7 - This is a measurement of the insulation between the transformer low
voltage winding and the high voltage winding. Connections are exactly the same
as for Test 5 and 6. Test mode is UST-R.